Galatea solar farm flips the switch

RIBBON CUTTING: ACT List MP Cameron Luxton, Micopro director Gerrard McCarthy, landowner Rory Gordon and Clenergy head of utility Yuneska Harris open the solar farm. Photos Troy Baker E6254-059

Troy Baker

A first-of-its kind project allowing for energy collection alongside standard dairy operations has opened in Galatea.

Approximately 200 people attended an open day at the Gordon Cattle and Solar Farm last week, keen to get a closer look at the project and hear from industry professionals about the planning, production and installation of its 7550 solar panels.

It’s a project that was seven years in the making and began with Rory Gordon contemplating possible future developments on his Grant Road property.

A conversation over a beer with friend Gerrard McCarthy, director of engineering procurement contracting company MicroPico, led to the plan for a solar farm with a difference.

The farm features a design believed to be a first for New Zealand, combining solar panels with sun-tracking technology that allows them to follow the sun and maximise energy production while accommodating cattle grazing beneath.

The panels are programmed to lie flat from late afternoon until the following morning, allowing cattle to graze unimpeded. The system automatically resumes power generation once the cattle have moved on each morning. Each supporting post stands 2.2 metres high, allowing stock to move freely around the site.

With the first stage complete, the farm has the capacity to generate 4.7MW of electricity, with 3.6MW fed directly into the local network.

Capable of supplying approximately 700 homes during daylight hours, the site can provide clean energy to the entire Galatea area.

The $7 million stage one project has a projected return on investment within seven to 10 years.

With an estimated lifespan of 35 years, the system requires very little maintenance, with only an annual visual inspection needed, along with additional checks before or after severe weather events.

Those attending the open day were also treated to an information session with Gordon, McCarthy, Act MP Cameron Luxton, who is a former builder and dairy farmer, and Yuneska Harris, head of utility at Clenergy, which supplied the technology.

McCarthy highlighted the importance of assessing land conditions before any infrastructure was installed.

“It’s important the land and soil are compatible and meet a certain standard, so pile testing and a geotechnical report are critical.

“We know of a couple of farms where the infrastructure is sinking. We also need to take wind risk into consideration, as the panels are sensitive to movement. We must consider the water table as well as the potential for liquefaction,” he said.

SOLAR INSTRUCTION: An expert panel takes questions from an-ag based audience. E6254-017

Being a first-of-its-kind project, there was considerabe behind-the-scenes work that had to be done.

“Looking back, we can see where processes can be streamlined so we are confident any future installations will take place over a much shorter time period”, he said.

Gordon said he was happy with how the project evolved. “Any issues we faced were easily overcome, so I’m glad it went so smoothly,” he said.

Luxton is optimistic about the future of New Zealand’s energy infrastructure.

“The demand for energy is huge, so combining agriculture and energy makes sense, as it’s another way for farmers to get a return,” he said.

McCarthy agrees with this sentiment.

“Modelling New Zealand’s energy prices is difficult and, as a result, large energy investment is rare, so smaller, localised projects such as this are the way forward.”

For the Gordon Cattle and Solar Farm, this is only the halfway point, with a second stage of development planned that will eventually see the solar panels cover 10 hectares.

OPEN TO VIEW: Members of the public and farmers inspect the new Solar farm. E6254-086